Electrical In Slab ITP
Site Name
Inspection Date
-
Month
-
Day
Year
Date
JDZ Installer/Inspectors Name
First Name
Last Name
Tilt Panel Drawing Number & Version
Does above noted tilt panel require electrical services installed?
Yes
No
Other
How many services or outlets required.
1
2
3
4
5
6
7
8
8 outlet - Visual inspection check box ( Tick Box if Yes leave unchecked if NO )
Has outlet location box been installed as per elevation
Have cable paths to outlets been installed
Does cable path maintain 25mm cover from front of pre cast slab
Have all cable paths been strung and sealed to prevent ingress of concrete and water.
Outlet 1
Outlet 2
Outlet 3
Outlet 4
Outlet 5
Outlet 6
Outlet 7
Outlet 8
7 outlet - Visual inspection check box ( Tick Box if Yes leave unchecked if NO )
Has outlet location box been installed as per elevation
Have cable paths to outlets been installed
Does cable path maintain 25mm cover from front of pre cast slab
Have all cable paths been strung and sealed to prevent ingress of concrete and water.
Outlet 1
Outlet 2
Outlet 3
Outlet 4
Outlet 5
Outlet 6
Outlet 7
6 outlet - Visual inspection check box ( Tick Box if Yes leave unchecked if NO )
Has outlet location box been installed as per elevation
Have cable paths to outlets been installed
Does cable path maintain 25mm cover from front of pre cast slab
Have all cable paths been strung and sealed to prevent ingress of concrete and water.
Outlet 1
Outlet 2
Outlet 3
Outlet 4
Outlet 5
Outlet 6
5 outlet - Visual inspection check box ( Tick Box if Yes leave unchecked if NO )
Has outlet location box been installed as per elevation
Have cable paths to outlets been installed
Does cable path maintain 25mm cover from front of pre cast slab
Have all cable paths been strung and sealed to prevent ingress of concrete and water.
Outlet 1
Outlet 2
Outlet 3
Outlet 4
Outlet 5
4 outlet - Visual inspection check box ( Tick Box if Yes leave unchecked if NO )
Has outlet location box been installed as per elevation
Have cable paths to outlets been installed
Does cable path maintain 25mm cover from front of pre cast slab
Have all cable paths been strung and sealed to prevent ingress of concrete and water.
Outlet 1
Outlet 2
Outlet 3
Outlet 4
3 outlet - Visual inspection check box ( Tick Box if Yes leave unchecked if NO )
Has outlet location box been installed as per elevation
Have cable paths to outlets been installed
Does cable path maintain 25mm cover from front of pre cast slab
Have all cable paths been strung and sealed to prevent ingress of concrete and water.
Outlet 1
Outlet 2
Outlet 3
2 outlet - Visual inspection check box ( Tick Box if Yes leave unchecked if NO )
Has outlet location box been installed as per elevation
Have cable paths to outlets been installed
Does cable path maintain 25mm cover from front of pre cast slab
Have all cable paths been strung and sealed to prevent ingress of concrete and water.
Outlet 1
Outlet 2
1 outlet - Visual inspection check box ( Tick Box if Yes leave unchecked if NO )
Has outlet location box been installed as per elevation
Have cable paths to outlets been installed
Does cable path maintain 25mm cover from front of pre cast slab
Have all cable paths been strung and sealed to prevent ingress of concrete and water.
Outlet 1
Take Photo
Does JDZ Installer/Inspector approve tilt panel to be poured?
Yes
No
JDZ Installers / Inspectors Name
JDZ Installers / InspectorsSignature
Does Builders Representative Approve Tilt Panel for pour?
Yes
No
Builder Representative Name
Builder RepresentativeSignature
Submit
Should be Empty: