AC CABLE (HV) TERMINATION AND TESTING
Inspection Checklist
Name
*
First Name
Last Name
Email
*
example@example.com
Test Location:
*
PCU11
PCU12
PCU13
PCU14
PCU21
PCU22
PCU23
PCU24
PCU31
PCU32
PCU33
PCU34
PCU41
PCU42
PCU43
PCU44
SWB01-FDR2
SWB01-FDR3
SWB02-FDR6
SWB02-FDR7
Click "Auto Complete Fields" button to populate form
150Cabtyp:
300Cabtyp:
150B1:
150R1:
150W1:
150B2:
150R2:
150W2:
300B1:
300R1:
300W1:
Testing Equipment Details:
*
Model #
Serial #
1
2
Termination and Pre-Testing actions and confirmations:
*
Yes
N/A
Verify that cables are de-energised and safe prior to termination
Testing equipment details have been recorded above
Check cables correctly supported below gland entry
Cables glanded and in correct position
Spacing between glands correct
Gland plates are secure and earthed correctly
Check that there is no physical damage to the cables or equipment
Check that cables are clearly marked with each phase colour
Check that the drain wires are fitted to all HV elbow connectors and are connected to the cable screen
1. Cable Type:
1. Termination Kit
NKT CPI 3
NKT CB 36-630
SWB - PCU Main Feeders:
Cable No.
11a. Earth/Screen continuity check
(record value)
11b. Polarity and continuity check
11c. Screen to Earth IR@1kV,
1 Min - Acceptance >40MΩ
(record value)
11d. HV Cable-Core screen IR @5kV,
1 min- Acceptance >5GΩ
(record value)
Ensure connector is cleaned, coated with paste, all bolts and/or nuts are tightened as per the manufacturers assembly instructions
Torque and Ductor Results
1
2
3
2. Cable Type:
2. Termination Kit
NKT CPI 3
NKT CB 36-630
PCU - PCU Feeders:
Cable No.
11a. Earth/Screen continuity check
(record value)
11b. Polarity and continuity check
11c. Screen to Earth IR@1kV,
1 Min - Acceptance >40MΩ
(record value)
11d. HV Cable-Core screen IR @5kV,
1 min- Acceptance >5GΩ
(record value)
Ensure connector is cleaned, coated with paste, all bolts and/or nuts are tightened as per the manufacturers assembly instructions
Torque and Ductor Results
1
2
3
4
5
6
Post Termination and Testing actions and confirmations:
*
Accept
Reject
Discharge all cable after insulation test (Min of 1min) and remove all leads, jumpers or bridges
Check that the HV cable screens are all solidly and separately connected and bolted to the HV earth bar
Confirm that phase rotation is correct and phase identification has been fitted
Cable terminations tightened, settings recorded in Comments field, and bolt heads marked
Cable ends labelled correctly
Ensure enclosure is free from dirt and debris
All penetrations correctly sealed
Attach image of each termination
All covers replaced and all bolts/screws checked for correct tension
Termination Kit installed using manufacturer guidelines
Comments:
Add Comments:
Signature
*
DateTime
EW Number:
*
Attach Files/Photos
Browse Files
Cancel
of
Do you want to make another submission?
Yes
Submit
Form: LLS_15F001-CS-E-0-003 Rev 2
Should be Empty: